As NextDecade Corp. progresses development on the primary three trains for its Rio Grande LNG mission in Texas, it’s working to agency up contracts for its second section by the center of the yr.
Houston-based NextDecade final yr broke floor in Brownsville, TX, on the primary three trains of the power, which might add 17.6 million metric tons/yr (mmty) of export capability to the worldwide market by 2027.
Whereas the early actions ramp up, administration has mentioned NextDecade is working to make a closing funding resolution (FID) on the two-train second section of the terminal by the top of the yr. In a latest mission replace, administration added the corporate is anticipating to finalize an engineering, procurement and development (EPC) contract with Bechtel Corp. by July.
[Download Now: In our 2024 Natural Gas Outlook Report ‘Future In Focus’, Natural Gas Intelligence’s experienced team of Thought Leaders delve into the myriad opportunities and questions the industry faces, with a focus on market dynamics, upstream outlooks and price forecast trends that will shape the future global natural gas landscape. Learn more.]
“With regulatory approvals in place, our Practice 4 and 5 growth capability is well-positioned to fulfill rising world demand for” liquefied pure fuel, CEO Matt Schatzman mentioned. “Supportive market situations present tailwinds to proceed progressing towards FID of Practice 4, which is effectively underway.”
Together with EPC negotiations, NextDecade is negotiating with potential contract holders for as much as 9.4 mmty in capability that might be obtainable from the growth, in accordance with the corporate.
NextDecade has estimated it might have no less than 3 mmty in mixed offtake lined from Trains 4 and 5 if TotalEnergies SE chooses to drag the set off on its fairness choices.
NextDecade reached FID on the primary section final summer season after securing $18.4 billion in financing, making it the most important greenfield vitality mission financing so far. TotalEnergies additionally agreed to a 5.4 mmty offtake and 16.67% fairness deal for Rio Grande’s first three trains.
TotalEnergies is presently the most important dealer of U.S. LNG and is the second largest LNG vendor on the earth. It has focused rising its LNG gross sales to 50 mmty by 2025.
NextDecade is trying to place one other 6 mmty beneath contract with extra patrons earlier than making an FID on section two, administration mentioned.
Each phases of Rio Grande LNG are presently unaffected by the Biden administration’s pause on LNG export authorizations. NextDecade has till 2027 to position section two in-service beneath its authorization from the U.S. Division of Power.
As for the primary section, the corporate mentioned development and engineering was on schedule. General, Trains 1 and a pair of had been round 14% full as of January. Engineering was 47.9% full, procurement was 26.8% full and development was 1% full.
Practice 3, which is being constructed on a separate timeline from the primary two trains, was reported at 4.4% full.
The publish NextDecade Appears to be like to Ink Contract with Bechtel for Rio Grande LNG Growth by July appeared first on Pure Fuel Intelligence