At 37.66 metres in size, 4.80 meters in diameter and weighing 130 tonnes, the arrival of the LNG tank at BioEnergie Park Güstrow, scheduled for mid-December this yr will mark one other vital – and above all, imposing – milestone within the conversion mission for Germany’s largest biogas plant with built-in bio-LNG unit so far, in accordance with EnviTec.
“To date, we now have already modernised and transformed 4 of the 5 modules to fulfill all the newest requirements,” defined Frank Hinken, managing director of EnviTec Bioenergie Güstrow. This conversion work consists of new agitators, superior pumping methods and double-membrane roofs. The final characteristic makes gasoline storage as capacious as doable whereas concurrently variable. Hinken added: “This implies biogas will be saved with out time limitations and upgraded on a versatile timeplan.”
Operating in parallel to this conversion work is one other mission to transform 4 giant focus tanks, every with a 15,000 cubic metre capability, into digestate tanks. Three new tanks will even be constructed. “That may then full tank development for now,” Hinken mentioned. At every development stage, between 20 and 60 workers from EnviTec Biogas and different corporations are exhausting at work on the 31 ha web site in Mecklenburg-Western Pomerania.
At the moment, two of the 5 high-pressure water scrubbing traces, which had been used to improve 1,000 Nm3 of biomethane per line, are nonetheless in operation. “The opposite traces have been dismantled, in order to create house for the deliberate CO2 liquefaction unit,” Hinken defined. The 2 future EnviThan gasoline upgrading models, which can change the previous high-pressure water scrubbing unit, are actually ready of their containers, already put in and examined, to be shipped to Güstrow. Foundations have already been poured for 3 of the 4 containers utilized by the progressive membrane upgrading know-how, with preparations for the fourth now in progress.
These conversions have been supplemented by work on a retention construction within the type of a compressed earth wall. This security barrier to dam substrate leaks is required to acquire a allow in accordance with part 16 of the Federal Immission Management Act. “The entire approval procedures have been accomplished with none points,” commented Birgit Bagert, managing director of von Lehmden Planning Consultants. “From the applying submission in 2021 onwards, everybody has labored as a workforce and each the preparatory work accomplished by EnviTec and communications with the authorities have been a mannequin of transparency and effectivity.”
With this plant, EnviTec Biogas mentioned it was setting a milestone for the transport sector. From its deliberate pilot operation within the second quarter of 2023, the Güstrow plant will purpose to produce important portions of purified bio-LNG to assist make heavy items visitors greener.
Quite a few agreements have already been signed with prospects seeking to provide this LNG as a substitute gasoline at their filling stations.